Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B  20.12.2017 The year 2017 is coming to an end and the crane on construction site Hauptbahnhof C.18.B can be dismantled on schedule even before the new year starts. All of the roof domes have been put up … Continued

Christmas party 2017

wga zt

The team from WGA ZT GmbH accepted the invitation and met up for dinner together in the “Pichlmaiers zum Herkner” restaurant. The Christmas party was celebrated in a relaxed atmosphere. Our Managing Director Harald Oissner gave plenty of praise to … Continued

Construction progress Wenhartgasse

Baufortschritt Wenhartgasse

Construction progress Wenhartgasse 18.12.2017 The floor structure including under-floor heating will also be laid once the drywalls have been completed. External work is also progressing; the roof structure is almost finished. Work on the street-side thermal insulation system was interrupted … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 18.12.2017 Building works have been progressing rapidly on plot 2 since the official start of construction on the 27.02.2017, The construction of the walls in the area of staircases 1, 2 and 3 on the … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 18.12.2017 The Christmas tree will soon be up in every living room and we will also soon be putting a tree on the roof for the topping-out ceremony! In section 3 just the last floor is … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 12.12.2017 Building work in the Anschützgasse is moving forward quickly. As you can see from the photos, the façade is just being finalized. Only the enamel glazing is missing from the dormers. The lower construction of the … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 30.11.2017 The shell is growing fast! Component 1 reached the planned high, component 2 is nearly as high as it supposed to be and in the component 3 there are still a few floors left to … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 28.11.2017 Since the official start of construction on 27.02.2017 the construction work on plot 2 is progressing rapidly. In the area of staircases 1, 2 and 3 the construction of the walls on the 3rd … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 24.11.2017 In part 1, the windows were completely installed and the drywall work is progressing rapidly. In the lower floors, the underfloor heating has started to be installed; soon the screed can be made here as … Continued

Topping-out ceremony Aspernstrasse 115

Gleichenfeier Aspernstrasse 115

Topping-out ceremony Aspernstrasse 115 23.11.2017 The roof has been reached at Aspernstrasse 115. This occasion was celebrated on 23.11.2017 together with two other projects of the developer Hart + Hart. Representatives of Hart + Hart developers, Auböck Baugesellschaft, WGA ZT … Continued