Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 38 30.08.2017 Since the start of construction in March, much has been done and the shell is soon completed. The interior development of the terraced houses is proceeding rapidly and the installation of the windows is … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wr. Neustadt

Construction progress Cityquartier, Wiener Neustadt 23.08.2017 The construction work on the property 2 is proceeding rapidly. The floor slab and the cellar walls have already been completely erected. In the area of the stairways 1, 2 and 3, the ceiling … Continued

Construction progress Messestrasse II

Baufortschritt Messestraße II

Construction progress Messestrasse II 22.08.2017 The cranes are turning like a prater ride business! Almost all the walls are on the ground floor and the ceiling above is partly concreted. Formwork for the walls on the first floor was started. … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof

Construction progress Hauptbahnhof C.18.B 21.08.2017 The shell has now been made up to the walls on the first floor. At the moment, the formwork, reinforcement and concrete work on the ceiling takes place over the first floor. It is easy … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 21.08.2017 The construction work progressed rapidly in Anschützgasse. The shell is standing and the traditional match tree has been set up. On the 13th of September we will have the same celebration. The Steildach is already covered. … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 21.08.2017 In accordance with the construction schedule, the outer facade is finalized in the installed residential building of component 1. For component 2, the facade has already been completed. Interior design (dry construction, electrical and building … Continued

End of construction Effenbergplatz

Effenbergplatz

End of construction Effenbergplatz 18.08.2017 On 18.08.2017 the two components Kaisermühlenstraße 12 and 16 were finished and as a general planner we were able to transfer the project successfully to our client. In only 17 months of construction the two … Continued

Construction progress Wenhartgasse

Construction progress Wenhartgasse 02.08.2017 Despite the enormous temperatures on the construction site, the shell is growing. As soon as the ceiling above the first floor was concreted, the first formwork and hollow walls were already on the second floor. The … Continued