Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 23.10.2017 The construction work on property 2 progresses rapidly. The floor slab and the cellar walls are completely built. Meanwhile the construction of the walls on the first floor has been completed in the area … Continued

End of construction Klitschgasse

Klitschgasse

End of construction Klitschgasse 7 16.10.2017 In cooperation with STRABAG AG as a general contractor, RE Klitschgasse Errichtungs GmbH successfully completed the residential building. 84 free-floated residential units, divided into 7 floors and 4 terraced houses, are ready for the … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 02.10.2017 The construction work at Anschützgasse is progressing rapidly. All drywall walls were placed in the office floors. The wet cells are already tiled. The lift has also been installed and the electrical and building services are … Continued

End of construction Köflacher Gasse 9

Köflacher Gasse 9

End of construction Köflacher Gasse 9 2.10.2017 STUWO AG’s student halls of residence at Köflacher Gasse 9 were ready for use at the start of the winter semester. The building is the second of STUWO AG’s halls in Graz and … Continued

Construction progress Wenhartgasse

Baufortschritt Wenhartgasse

Construction progress Wenhartgasse 27.09.2017 The ceiling above the last attic floor has been concreted, also the shell of the driveway is already finished. Therefore was the crane this week dismantled. On the first floor the drywallers are almost finished with … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 27.09.2017 Despite the autumn weather the work on the construction site is progressing. The formwork for the walls on the second floor has almost been completed. A large part of the reinforced concrete walls on this … Continued

Construction progress Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 26.09.2017 The floor slab and the cellar walls have already been completely erected. In the area of the stairways 1, 2 and 3, the construction of the ground floor walls has now been completed. In … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 25.09.2017 In accordance with the construction schedule, the outer facade, similar to component 2, has now also been completed in the residential building of component 1. The interior design (dry construction, electrical and building services installations) … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 25.09.2017 The shell is growing! Both cranes are working diligently. The ground floor is already concreted together with the ceiling. There are already walls on the third floor. The formwork of the ceiling above is in … Continued

Topping-out ceremony Wagramer Strasse

Topping-out ceremony Wagramer Strasse 20.09.2017 The topping-out ceremony for the building project Wagramer Strasse 38 took place on Wednesday, 20.09.2017. Representatives of STRABAG AG, Antigua Immobilien- und Handelsgesellschaft m.b.H., WGA ZT GmbH and many other participating companies followed the invitation … Continued