Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 21.08.2017 The construction work progressed rapidly in Anschützgasse. The shell is standing and the traditional match tree has been set up. On the 13th of September we will have the same celebration. The Steildach is already covered. … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 21.08.2017 In accordance with the construction schedule, the outer facade is finalized in the installed residential building of component 1. For component 2, the facade has already been completed. Interior design (dry construction, electrical and building … Continued

End of construction Effenbergplatz

Effenbergplatz

End of construction Effenbergplatz 18.08.2017 On 18.08.2017 the two components Kaisermühlenstraße 12 and 16 were finished and as a general planner we were able to transfer the project successfully to our client. In only 17 months of construction the two … Continued

Construction progress Wenhartgasse

Construction progress Wenhartgasse 02.08.2017 Despite the enormous temperatures on the construction site, the shell is growing. As soon as the ceiling above the first floor was concreted, the first formwork and hollow walls were already on the second floor. The … Continued

Construction Progress Eckertstrasse

Baufortschritt Eckertstrasse

Construction Progress Eckertstrasse 27.07.2017 The shell is finished. Portals and windows are already in place. At present, the complete thermal protection facades are produced. On the north side you can already see a finished section. At the same time, the … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 25.07.2017 In accordance with the building schedule, the exterior insulation is installed in components 1 and 2. In the case of component 2, the facade has also already been completed. The interior construction (dry construction, electrical … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 21.07.2017 The dismantling of the excavation protection is in process and the backfilling has already been made to large parts. The ground-floor walls are already standing, the first panels for the ceiling above the ground floor … Continued

Construction progress Effenbergplatz

Baufortschritt Effenbergplatz

Construction progress Effenbergplatz 21.07.2017 We are approaching the finish line in speedy steps. The last painting work is carried out in component 3, the walls and the ceilings are painted in the aisles and in the stairwell. Also the flooring … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 20.07.2017 The project at the Central Station C.18.B takes shape. After the reinforced concrete walls and columns on the ground floor, the ceiling was finished on the ground floor in the middle of this month. At … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 19.07.2017 Since the official start of the construction on 27.02.2017, the construction work on the property 2 progresses rapidly. The floor slab is completely concreted and the basement walls have already been built almost completely. … Continued