Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 17.07.2017 Construction works well. Meanwhile, the first wooden walls were placed on the 5th floor. The two upper floors are designed as residential buildings and offer already an impressive view over the rooftops of Vienna. Furthermore the … Continued

Construction progress Wagramer Strasse

Construction progress Wagramer Strasse 11.07.2017 In the street-side building, the ceiling above the second floor was concreted and the first apartments could be viewed on the first floor. The shell of component 2 has been completed and this week we … Continued

Construction progress Wenhartgasse

Wenhartgasse

Construction progress Wenhartgasse 04.07.2017 After six weeks of construction at the cellar, the cellar ceiling was concreted at the end of last week. The hollow walls on the ground floor are for the most part set up and are to … Continued

Construction progress Aspern J12

Construction progress Aspern J12 26.06.2017 In the installed residential building of components 1 and 2, the outer insulation is applied. In the case of component 2, the south-east facade has also already been completed. Interior construction (dry construction, electrical and … Continued

Construction progress Cityquartier, Wiener Neustadt

Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 19.06.2017 The construction work on the plot 2 progresses rapidly. The floor slab is almost completely concreted and about half of the basement walls have already been erected. The corresponding production elements for the erection … Continued

Construction progress Effenbergplatz

Effenbergplatz

Construction progress Effenbergplatz 16.06.2017 The thermal insulation composite facade has been finished in component 3. Further, the railings were installed on the balconies. In the interior, laminate floors and tiles are laid in the upper floors. Component 4 is successively … Continued

Construction progress Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B Favored by the weather, work on the construction site is proceeding rapidly. The ceiling above the ground floor and the largest part of the columns on the ground floor has already been completed. At stair 1, … Continued

Construction progress Messestrasse II

Construction progress Messestrasse II 14.06.2017 Construction work is progressing well. The foundation plate is already finished and the majority of the walls and supports from the ground floor are already standing. The ceiling from the ground floor is mostly switched … Continued

Construction progress Anschützgasse

Anschützgasse 1

Construction progress Anschützgasse 12.06.2017 The summer temperatures provide the best building conditions in Anschützgasse 1. All wooden walls and beams have already been installed on the 4th floor and half of the hybrid ceiling on the 5th floor has already … Continued

Topping-out ceremony Aspern J12

Aspern J12

Topping-out ceremony Aspern J12 31.05.2017 The Topping-out ceremony for the building project Aspern J12 took place on a beautiful sunny Wednesday. Representatives of STRABAG AG, WGA ZT GmbH, Freimüller Söllinger Architecture, WBV GÖD, Erste ÖSW, STUWO AG, Aspern J12 GmbH, … Continued