Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 22.02.2018 While there is snowfall outside and freezing temperatures, the construction work inside the building continues diligently. The screed has already been laid on the 2nd and 3rd floors of staircase 2, while the vapour barrier is … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress  Anschützgasse 20.02.2018 The construction work in Anschützgasse is progressing rapidly. The upper end of the superior steel structure has already been covered with sheet metal and the sheet metal partitions were installed as well. Half of the façade … Continued

End of construction Eckertstrasse

Baufertigstellung Eckertstrasse

End of construction Eckertstrasse 09.02.2018 The project Eckertstrasse 30 is successfully completed. The handover of the apartments in our building part to Erste Immobilien KAG took place on February 8 – 9. At that time, the kindergarten was already in operation … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 09.02.2018 In construction phase three, the basement walls are currently being formed and reinforced on the finished foundation slab. In construction phases one and two, the basement ceiling has already been completed. The prefabricated parts for … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 06.02.2018 Building work on the Anschützgasse is progressing rapidly. The protruding steel construction on the facade facing the Wienzeile on the left has been extended at the upper and lower ends. This has also been completed in … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 02.02.2018 In both components, the drywall construction work has been completed and the floor heating and screed have been completely installed on all floors. The crane was removed and the recess in the foundation plate was … Continued

Construction progress Messestrasse II

Kurt Hörbst

Construction progress Messestrasse II 29.01.2018 Because we just love building sites, we have commissioned a professional photographer to take some artistic shots of our project.In these snapshots you can see that the structural work is almost finished. There is just … Continued

Construction progress Wenhartgasse

Baufortschritt Wenhartgasse

Construction progress Wenhartgasse 29.01.2018 The pavement has been finished and the base of the fence has been concreted. Surfacing work in the garage has also been completed. The walls are being tiled in the flats. The painters and drywall builders … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt  26.01.2018 The building works on Plot 2 are moving ahead rapidly! Construction of the walls in the area of stairwells 1, 2 and 3 has been completed. On staircase 3, the concrete ceiling on the … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 22.01.2018 The crane is gone… the building shell is in place… the interior work is underway… and the construction site at Hauptbahnhof C.18.B is about to start the new year full of energy. The drywall construction … Continued