Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 22.01.2018 In the new year, the construction work in Anschützgasse will continue apace. The facades were already finalised, with the exception of a few complementary tasks and the steel construction in front of the facade to the left … Continued

Construction progress Aspern J12

Aspern J12

Construction progress Aspern J12 15.01.2018 In accordance with the construction schedule, building section 1 and building section 2 are due to be completed imminently. Interior work (drywalls and the installation of electrical system and building services) in building sections 1 … Continued