End of construction Aspernstrasse 115

Aspernstraße 115

End of construction Aspernstrasse 115 01.08.2018 In cooperation with AUBÖCK BAU GMBH as general contractor, the residential complex Aspernstrasse 115 in 1220 Vienna was completed for HART & HART Bauträger GmbH. The 21 apartments and 12 parking spaces are now … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 30.07.2018 The project Hauptbahnhof C.18.B is already on the finishing line. While completion work is still in progress on the residential floors, the office space in the building has already been completed and handed over to … Continued

End of construction Wagramer Strasse

End of construction Wagramer Strasse 38 27.07.2018 In cooperation with STRABAG AG as general contractor, the residential complex Wagramer Strasse 38 in 1220 Vienna was completed as planned for Antigua Immobilien- und Handelsgesellschaft. The 37 apartments, 5 terraced houses and … Continued

Construction progress Kindergarten Ebergassing

Baufortschritt Kindergarten Ebergassing

Construction progress Kindergarten Ebergassing 19.07.2018 The construction work of the kindergarten is progressing rapidly. The floor slab was concreted and all concrete and brick walls are already on the ground floor. Soon the concrete ceiling above the ground floor will … Continued

Construction progress Paulusgasse

Baufortschritt Paulusgasse

Construction progress Paulusgasse 19.07.2018 For the Paulusgasse construction project we want achieve big goals , so the crane is already in place. The work on the excavation pit support has been completed and the next step is the construction of … Continued

Aspern J4, Vienna – Construction progress

Because of the good weather in the last few weeks, the construction work in Seestadt is progressing well .The excavation pit support is largely completed, the first sections of the base plate are concreted and the cranes have grown to … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 16.06.2018 The construction work is making good progress on all three construction sites. On lot 2, in the area of staircases 1, 2 and 3, the installation of the external facade insulation is completed and … Continued

Topping-out ceremony Stadlbreiten 9+11

Gleichenfeier Stadlbreiten 9+11

Topping-out ceremony Stadlbreiten 9+11 12.07.2018 The Topping-out ceremony took place on 12.07.2018 in sunny but windy weather for the new construction of the Stadlbreiten residential complex. The representatives of at home Immobilien-GmbH, STRABAG AG, WGA ZT GmbH and many other … Continued

Saltenstrasse 1, Vienna – Construction start

In Saltenstrasse 1, work has begun on 46 new apartments in a well-developed green area. The work started with the securing of the excavation pit and the deep drillings for the geothermal system. After the site has already been cleared … Continued

New on YouTube

Hauptbahnhof C.18.B In the following video we have prepared for you some impressions of the Topping-out ceremony including a short tour of the construction site! The video is available here. <<more videos>>