Stadlauer Strasse 64, Vienna – Construction progress

Most of the structural work has now been completed and the interior work is progressing rapidly. Currently, the underfloor heating systems are being installed in stairways 3, 4 and 6 and the floor screeds are being laid, while the building … Continued

Construction progress Miriam-Makeba-Gasse

Construction progress Miriam-Makeba-Gasse 10.12.2019 Only a few weeks left until the project is completely finished! In the interior, the parquet and tile floors were finished and the last construction works were completed in order to be able to start with … Continued

End of construction Grundäckergasse II

End of construction Grundäckergasse II 10.12.2019 The 3 building sites with 7 building components, 9 staircases, and the common parking garage are completed and will progressively be handed over to the tenants. The on-schedule handover of 331 apartments within this … Continued

Rugierstrasse 55, Vienna – Construction progress

The soil was loaded continuously onto trucks and transported off the construction site until it reached the excavated bottom. The drilling rig for the geothermal probes is now in operation there and has already drilled more than half of the … Continued

End of construction Hauptbahnhof C.16.D

End of construction Hauptbahnhof C.16.D 28.10.2019 After a construction period of only 13 months, the new residential building in the Bloch Bauer Promenade 17 was handed over to our client, WBV GFW, on 28/10/2019 as scheduled. In cooperation with the … Continued

Construction progress Grundäckergasse II

Construction progress Grundäckergasse II 22.11.2019 The final tasks before the three construction sites are finished have already reached their final stage. The outside facilities, which are also almost ready, give an idea of the future look. In the courtyard area, … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 22.11.2019 In a shining white, plaster facade appears after the scaffolding has been dismantled. This completes the building exterior of the upper floors. Accordingly, the construction work on the exterior facilities has now been started and the … Continued

Hofwiesengasse 12, Vienna – Construction progress

Before the start of the winter, construction work is being carried out at the exterior of the building. The carpentry work is already finished and the plumbers are currently finishing the steep roof. Also on the green roofs, the last tasks are … Continued