The building has already withstood the first dry snow and the construction work continues to progress at a remarkable pace despite a somewhat tough winter. The interior plastering is in place, all the building services installations are installed and the … Continued
In a construction time of 19 months, 67 flats, six accommodation rooms, and two commercial areas including as well as a parking garage were built in the district of Kagran in cooperation with contractor STRABAG AG. The housing complex consists … Continued
The year 2020 is coming to its end and the completion date is gradually approaching at the BC Aron Menczer construction site. The installation of the glassed-in areas is almost finished. Parts of the building have also been equipped with … Continued
We can proudly announce that one of our largest projects was finished after 27 months of continuous construction. Right on time for the official handover date at the end of November 2020, the Stadlauer Strasse 64 project in Vienna’s 22nd … Continued
In both building sections, the fillings, impact sound insulation and underfloor heating pipes have been installed continuously and quickly. According to the planned construction schedule, the work was timed in such a way that the screeds were laid first in … Continued
The interior works at the Liselotte Hansen – Schmidt Education Campus are progressing well. Currently, the floor screed work and the installation of the suspended ceilings are being carried out in some parts of the building. The suspended ceiling in … Continued
After a construction period of 13 months, an additional residential building complex in a modular wooden construction style in co-operation with Lukas Lang Building Technologies GmbH, as general contractor for LZH Landzinshaus GmbH, is finished. The residential building complex is … Continued
Inside of staircase 2, the drywalls were sealed after the installations was completed. Here the pouring of the fill is already in progress as a first stage of the screed work. In staircase 1, the electrical and sanitary installations are … Continued
The PRISMA components (components N5-N8) have been completed. A total of 77 flats including garage space have been built and are now ready for their future use. Some flats have already been occupied. Whilst the new occupants are already moving … Continued