Merry Christmas 2021
Our office will remain closed from 12/23/2021 till 01/09/2021. We will be available to help you again from the 01/10/2022. We wish you happy holidays and a prosperous new year!
Our office will remain closed from 12/23/2021 till 01/09/2021. We will be available to help you again from the 01/10/2022. We wish you happy holidays and a prosperous new year!
In the northern section of the building, the concrete work is almost completed and the angled end of the building is clearly visible. The drywall has been installed in a number of flats and the windows have already been fitted. In the … Continued
The construction site is rising in height, divided into three construction phases. In the meantime, both cranes are now running. In the first construction phase, the walls of the ground floor have already been installed and the concreting work for the ceiling … Continued
Even the brief outbreak of winter could not stop the progress of the structural work. The foundation slab’s reinforcing work was mostly completed, and it can still be concreted before the Christmas break. The pipes of the deep wells are clearly visible, … Continued
Currently, only 10% of the students manage to find a room in a student hall of residence. At the same time, it is especially important for young students to live inexpensively and in proximity to their educational institution. The problems concerning … Continued
Currently, steel structures of various sizes are being installed to reinforce the existing ceilings in the area of the subsequent wall and ceiling openings. The installation work has already started in building section A. The location of the future shafts for the … Continued
On the construction site Schäffergasse 10-12 in Vienna’s 4th district, the construction work has now started and the securing of the foundation pit was already accomplished. The soil moving work are currently in progress so that the installation of the … Continued
The interior construction work of the students’ dormitory is already progressing rapidly. Last week, the scaffolding of the northern wing was completely dismantled and the adjacent building was dismantled as well. The electrical installation and the drywall work continued and the … Continued