The façade of the Ameisgasse 28 development is slowly coming into view.
The noise barrier has been dismantled and removed, and the facade is currently being insulated.
The room-high fixed glazing on the 2nd floor is being installed on the street side, and the steel structure for the canopies of the flat entrance doors is being installed in the portico.
The facades facing the courtyard are already insulated and plastered.
The plumbers are also working quickly so that most of the gutters are already in place.