Significant structural work is currently being carried out in various parts of the building as part of the construction project.
The vertical walls of section A have been cast and the cladding removed. This gives a first impression of the appearance of the ground floor façade. The on-site concrete construction is supported accordingly. In component D, the high formwork panels of the ground floor will be removed once the concrete has set. The formwork for the ground floor of section C will then be erected. Meanwhile, structural work is underway in the basement of Component B. As components A and D have three more upper floors than components B and C, they are still at an advanced stage of construction.