Construction progress Anschützgasse

Construction progress Anschützgasse 12.06.2017

The summer temperatures provide the best building conditions in Anschützgasse 1.
All wooden walls and beams have already been installed on the 4th floor and half of the hybrid ceiling on the 5th floor has already been laid.
Only the two top floors are missing.
Parallel to this, the windows are mounted from the ground floor to the 4th floor.
The drywall will begin next week.

 

<<see project>>