Educational Campus Aron Menczer, Vienna – Completion of the project

After a month of hard work on the Aron Menczer educational campus, the construction work on the mullion and transom as well as on the alucobond facade has been completed and the first ceramic components have been installed along the pedestrian and bicycle ramps. The interior work is also progressing steadily. Several trades are being completed in sections and on the ground floor, the final flooring was installed in almost all the rooms. In order to meet the deadline, various skilled contractors are now completing their work and finalising their tasks in the whole building. In order not to interfere with each other, the trades are distributed over the six floors and alternate in a systematic fashion. Given these conditions, the education campus should be able to open its doors on time in autumn of 2021.

 