Construction progress Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 23.08.2017

The construction work on the property 2 is proceeding rapidly.

The floor slab and the cellar walls have already been completely erected.

In the area of the stairways 1, 2 and 3, the ceiling above the cellar floor is made and the ground floor walls are erected immediately before the completion. At Stiegenhaus 3, the walls on the first floor are also beginning.

The finished parts for the element ceilings of the remaining areas around the Stiegenhaus 4 are continuously supplied to the construction site or the sections and sections where local concrete is used, the necessary formwork and reinforcement are produced.

 