Construction progress Hauptbahnhof C.18.B
Favored by the weather, work on the construction site is proceeding rapidly. The ceiling above the ground floor and the largest part of the columns on the ground floor has already been completed. At stair 1, the remaining supporting walls are currently being built. In the area of stair 2, the formwork and reinforcement of the ceiling above the ground floor, including the component activation activated in the reinforced concrete, is already being created at the same time. In the coming week, the retaining wall will also be built on the neighbouring site.