Construction progress Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 27.09.2017

Despite the autumn weather the work on the construction site is progressing. The formwork for the walls on the second floor has almost been completed. A large part of the reinforced concrete walls on this floor was already concreted and could already be switched off again. The finishing elements for the ceiling above the second floor at staircase 2 are being moved and afterwards concreted.
The installation of the balconies is also progressing steadily; the first balcony slabs are offset on the third floor, while the steel concrete bridges can already be installed on the second floor.

 