Construction progress Wagramer Strasse 01.06.2017
The warm weather offers very good conditions on the construction site!
The ramp was concreted and the walls on the ground floor completely erected.
In calendar week 21, the ceiling was concreted above ground in component 2 and this week the ceiling in component 1 was finished.
The formwork and the iron for the walls on the second floor were also set up and laid.