There is again some progress to report on the remediation work in the Canisianum dormitory. Now that the screed has been laid in the middle wing and the sealing work has been completed, the tiles are being laid in the bathrooms. In the corridor, the terrazzo frieze is currently being prepared. Meanwhile, drywall, filling and sanding work continues. After the excavation work of the outdoor facilities, the substrates and humus were laid in the east courtyard. The steel angles and steel strips that will form the transition between the planting and the gravel surface, as well as the first curbstones, have been moved for the most part. The renovation of the façade on the south side has begun. The restorers are busy cleaning and repairing the natural plaster surface and coats of arms.