Saltenstrasse 1, Vienna – Construction progress

In the complete building, the screed was already placed and also heated out. The apartments on the first floor of staircase 1 are now equipped with controlled ventilation from the ground-floor to the upper floor. Afterwards, the installation of the … Continued

Hofwiesengasse 12, Vienna – Construction progress

The construction work is progressing well even though the weather conditions are fluctuating.  The facades of building units one and two are finished and the scaffolding was taken down. The scaffolding for the third building unit was also removed on … Continued

Rugierstrasse 55, Vienna – Construction progress

The construction work on the basement is progressing rapidly. While the remaining floor slabs are being built, the first basement walls were set up at the back end of the property. From there, the construction site has then progressed onwards … Continued

Saltenstrasse 1, Vienna – Construction progress

All of the floor structures and underfloor heating have now been placed in staircase 1 and the concrete pavement has been added to all the floors. At the lower tops, the concrete screed has been completely preheated and the filling work … Continued

Rugierstrasse 55, Vienna – Construction progress

The installation work on the collection pipes for the geothermal energy was fully finalised. After that, the different shafts were installed, reinforced and concreted underneath the base plate. Following these preparations were successfully carried out, the first area of the … Continued

Gailenbachweg 5, Salzburg – Construction progress

The construction of the building structure for all eight new building units is now ready! At this point, the last windows and the post-and-beam facades will be installed for the building units N1-N8. The railings, as well as the room-high … Continued

Saltenstrasse 1, Vienna – Construction progress

The insulation on the facade is already almost completely in place while waiting for suitable weather conditions for the following working stages. For the time being, the construction work inside the staircase 1 is continuing without interruption. The underfloor heating was installed … Continued