Construction progress Weinzingergasse

Construction progress Weinzingergasse 19.12.2019 In front of the house, the asphalt work was finished and the construction site equipment was removed so that the pavement can now be freely used again. In the interior, the tiling work is finished and … Continued

Aspern J4, Vienna – Construction progress

The portals of the Caves were installed in the last days and most of the windows have already been moved. While the first surfaces of the thermal insulation composite system are being applied, the wooden façade of the other components … Continued

Saltenstrasse 1, Vienna – Construction progress

The first sections of the scaffolding were dismantled, with the fresh, bright white facade of staircase 2 standing out. Inside, the screed has already been completed and the heating phase has now started. At the same time, the installation of … Continued

Stadlauer Strasse 64, Vienna – Construction progress

Most of the structural work has now been completed and the interior work is progressing rapidly. Currently, the underfloor heating systems are being installed in stairways 3, 4 and 6 and the floor screeds are being laid, while the building … Continued

Construction progress Miriam-Makeba-Gasse

Construction progress Miriam-Makeba-Gasse 10.12.2019 Only a few weeks left until the project is completely finished! In the interior, the parquet and tile floors were finished and the last construction works were completed in order to be able to start with … Continued

Rugierstrasse 55, Vienna – Construction progress

The soil was loaded continuously onto trucks and transported off the construction site until it reached the excavated bottom. The drilling rig for the geothermal probes is now in operation there and has already drilled more than half of the … Continued

Construction progress Grundäckergasse II

Construction progress Grundäckergasse II 22.11.2019 The final tasks before the three construction sites are finished have already reached their final stage. The outside facilities, which are also almost ready, give an idea of the future look. In the courtyard area, … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 22.11.2019 In a shining white, plaster facade appears after the scaffolding has been dismantled. This completes the building exterior of the upper floors. Accordingly, the construction work on the exterior facilities has now been started and the … Continued