Hofwiesengasse 12, Vienna – Construction progress

All of structural work has now been completed. The construction work on the roof of structural element 1 has already been completed. The drywall construction has already been completed in structural elements 1 and 2 and the backfill has been … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 26.09.2019 Three sides of the building already shine in bright white of the finished plaster coating. The insulation that makes up the EWIS has already been applied to the street façade along with the various structural elements. … Continued

Construction progress Paulusgasse

Construction progress Paulusgasse 24.09.2019 The scaffolding on the street side of Paulusgasse was already removed and now the facade shines in full splendour! Inside the courtyard, the facade work is currently being completed. The floor surfaces in many apartments were … Continued

Saltenstrasse 1, Vienna – Construction progress

The construction on the last steel-concrete floor is progressing well. The parapet walls and the elevator shaft will be moved on top of it, which will complete the framework construction in the upcoming week. At the same time, the roof … Continued

Construction progress Miriam-Makeba-Gasse

Construction progress Miriam-Makeba-Gasse 04.09.2019 The overall completion is slowly getting closer. The building shell is now completely finished, the mullion-transom façade, the lift and the windows have been installed. The dry construction work in the flats has already been completed … Continued

Construction progress Hauptbahnhof C.16.D

Construction progress Hauptbahnhof C.16.D 02.09.2019 Our housing project at Bloch-Bauer-Promenade 17 in 1100 Vienna is finally on the home straight. The final guttering work will be completed on the façade and the loggias will also receive their partition walls in … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 23.08.2019 Another important step is completed: the concrete screed is finished in all areas. And despite the summer temperatures, heating is now taking place in the building to carry out the screed heating process. Simultaneously, the exterior … Continued

Construction progress Hofwiese, Mitterndorf a. d. Fischa

Construction progress Hofwiese, Mitterndorf a. d. Fischa 22.08.2019 During the two months since the start of the construction work, the progress of construction work in Mitterndorf an der Fischa is progressing rapidly. After concreting the foundation slabs of the two … Continued

Saltenstrasse 1, Vienna – Construction progress

In a continuously rapid construction progress, the reinforced concrete work is developing up to the top. Meanwhile, the staircase 2 has received a complete attic storey with a closed building roof. Here the first preparations for the extension were already … Continued