Construction progress Anschützgasse 05.03.2018
Despite the icy temperatures, the construction work in Anschützgasse is progressing rapidly. With the installation of the last lamellas, the façade work is entering its final phase, the office floors have already been totally completed and individual completion work is currently still being carried out on the ground floor. In mid-March, a partial handover to the new tenants will take place.
In the apartments, all floors have already been laid and the kitchens installed. At the same time, work on the outdoor facilities is also in full swing.