Construction progress Aspern J12 25.07.2017
In accordance with the building schedule, the exterior insulation is installed in components 1 and 2. In the case of component 2, the facade has also already been completed.
The interior construction (dry construction, electrical and building services installations) is progressing rapidly in component 1 and is approaching completion. Flooring work has already started in components 1 and 2. At the moment, the tiles in the sanitary areas in component 2 and the floors in the living areas in component 1 are being laid.
In the building 3, which is located at the Sonnenallee, the drywall construction is about to be completed.
Only the first floor and the ground floor are left out in regard to the floor construction and the screed. The furnishing of the building for the coming façade work is just before the finalization and the fitting of the exterior insulation is already in a very advanced state.
In the case of component 4, the garage, the roof sealing work could be completed and the work on the outdoor systems has already begun.