Aspern J4, Vienna – The construction work on the multifunctional building known as Sirius is coming to an end

The construction work continues and is slowly coming to an end. The first units in section B1 have already been completed. In the general areas, the floor and wall coverings are being manufactured and the installations are being completed. The assembly of the gymnasium equipment is also almost finished. In building section B2 the drywall construction work is finished. Currently, all floor and wall coverings are being installed there. The work on the basement partition walls is also continuing. In building section A, the work on the suspended ceilings on the ground floor is in the final phase. The floor and wall tiles have already been laid in the first apartments and the parquet flooring has also been installed in some of the units. You can see from the outside that the work on the wooden façade of building components B1 and B2 is almost finished and that the first concrete slabs have been poured in the interior courtyard.

 