Construction progress Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 19.07.2017

Since the official start of the construction on 27.02.2017, the construction work on the property 2 progresses rapidly.
The floor slab is completely concreted and the basement walls have already been built almost completely. Meanwhile in the area of the stairways 1, 2 and 3, the ceiling above the cellar floor has been established and the construction of the ground floor walls has already begun.
The finished parts for the element ceilings of the remaining areas around stairway 4 are continuously delivered to the construction site.

 