Construction progress Cityquartier, Wiener Neustadt 16.06.2018
The construction work is making good progress on all three construction sites. On lot 2, in the area of staircases 1, 2 and 3, the installation of the external facade insulation is completed and the installation of the external railings in the area of balconies and terraces is about to be finished. The dry wall construction work inside the building is also near completion. In the meantime, the carpentry work on stairwell 4 of lot 2 has been completed and the work on the facade has already started. On lot 1 the ceiling above the 3rd floor is finished and the work on the walls in the attic is in full progress. Work is currently in progress on the walls of the back lot 3 on the ground floor.