Educational Campus Seestadt Aspern North, Vienna – Construction progress

The construction work on the educational campus is progressing very well. The ground floor – floor slab at building element C is almost ready, at building element A the ground floor – concrete steel walls and precast columns are placed and the ceiling above the ground floor is partially concreted. In the coming weeks, the construction will go on on at the ground floor and at the same time, the 1st floor (concreting section 1) will also be started.

 