After the Christmas break, the construction work on the education campus continues cheerfully. In the building area A, the walls on the first floor are being shuttered, as well as the ceiling above the ground floor in the building area B. The ground floor walls of the building area C are already finished and the prefabricated columns on the first floor are already partially in place. In the upcoming weeks, the construction work will continue on the 1st floor. At the same time, the sewer will be installed in the soil and the shafts will be repositioned. In area D (youth center) the panels for the sewer and the floor slab are under construction.