Construction progress Hauptbahnhof C.16.D 13.11.2018
We have made a good start – the crane is standing and the construction pit is secured. As only minor digging work was necessary on this site, the foundation work has already started. At the moment, the iron benders are busy preparing the base plate for reinforcement. In the next few days, the second part of the base plate can be concreted thanks to the continuing excellent weather. As a result, the new residential building at Hauptbahnhof Bauplatz C.16.D will rise rapidly.