Construction progress Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 22.01.2018

The crane is gone… the building shell is in place… the interior work is underway… and the construction site at Hauptbahnhof C.18.B is about to start the new year full of energy. The drywall construction work in the apartments on the 2nd floor of staircase 2 has already been completed and the filling work has begun. The 3rd floor will be completed by the end of January and the first screed work will start next week. The planking on one side of the 4th floor of staircase 2 was closed on one side and the first drywall construction work could also be started on staircase 1, on the 2nd floor. Large parts of the wall and ceiling insulation have already been installed in the basement. After removing the crane foundations, the inner courtyard was filled in and at the same time the pipes to the infiltration rig were laid. Meanwhile, the foundations are being prepared for moving the raised beds.

 