Construction progress Hofwiese, Mitterndorf a. d. Fischa

Construction progress Hofwiese, Mitterndorf a. d. Fischa 22.08.2019

During the two months since the start of the construction work, the progress of construction work in Mitterndorf an der Fischa is progressing rapidly. After concreting the foundation slabs of the two building components, the construction of the ground floor supporting structure and the related ceiling started. The façade elements of the ground floors were installed and currently, the supporting structures and roof sealings of the first floor are under construction.

 