Step by step we are approaching the end of the structural work in the basements. The interior walls are in place and the ceiling above the 1st basement floor has already been concreted in its first part (near Ichagasse). In the second section (near Kendegasse) the reinforcement has already been removed and the concreting will begin shortly. In the middle section, the ceiling above the 1st basement level is currently being shaped and the reinforcement is ready for further laying. The pulling of the sheet piles will probably start in calendar week 36.