In the 21st district the construction project “Leo” is slowly growing out of the soil. In the last few weeks, the sheet piles were pulled and the formwork elements were delivered from the warehouse located in Lower Austria.
The production of the walls on the ground floor is going on simultaneously in the first and second sections. In the third section the necessary formwork for the next walls is already in place. As soon as the walls on the first and second sections have been completed, the construction of the walls in section three will start.