Construction progress Messestrasse II 21.07.2017
The dismantling of the excavation protection is in process and the backfilling has already been made to large parts.
The ground-floor walls are already standing, the first panels for the ceiling above the ground floor have been installed and the ramp of the garage entrance is concreted.