Construction progress Messestrasse II 27.04.18
After the Topping-out ceremony, work is once again carried out on the construction site.
The thermal bonding system is attached to the facade, windows and mullion-transom facade are diligently installed, plasterboard walls are placed, porcelain stoneware tiled and installations laid. Work is also progressing in the inner courtyard. The substructures of the external stairs are mounted.