Construction progress Miriam-Makeba-Gasse 26.06.2019
Thanks to the good weather, the roof lining could be sealed as planned and the black tiling work could be finalized. The windows are already in place up to the 4th floor and the dry construction has now reached the last floor. As a result, we can begin with the work on the thermal insulation composite system. Now that the supply lines for the underfloor heating and the electrical wiring are already in place, the backfill is currently being added. On the ground floor, we are working simultaneously on the post-and-beam facade in order to completely close the structural work.