Construction progress Parking deck Oberwart

Construction progress Parking deck Oberwart 15.11.2018

Since the ground-breaking ceremony on October, 2nd, 2018, the construction work is now progressing rapidly. After the digging, the quiver and strip foundations for the prefabricated components lying above were manufactured. Since all external supports of phase I had already been installed, the height and volume of the future parking deck are already visible. As soon as the cavity walls in the lowest two levels are completely offset, the first cavity planks for the ceiling of level 0 are ready to be laid.

 