Construction progress Parking deck Oberwart 12.04.2019
All steel beams, light purlins and trapezoidal sheets were installed, so the roof is now completed. Now that the concrete has already been laid, it will soon be possible to start coating the surfaces of the parking floors. The manufacture of the outdoor facilities is running at full speed. The construction of the subsoil for the retention system and the green seepage pits as well as the laying of the external canal are already done.