After a relaxing Christmas break, the construction work is now progressing with fresh enthusiasm and energy. Now that the screeds are hardened and ready to be walked on, the first preparations are being made to start the heating process here. In the meantime, the drywall builders are working on the wall cladding in the corridors in order to install the floor structures according to the schedule. The scaffolding on the façade was removed last year so that the remaining railing panels can now be installed. The roof superstructures with the substrates and foundations for the pathways and the green spaces are being built in the rear area of the property for the time being.