Rugierstrasse 55, Vienna – Construction progress

The soil was loaded continuously onto trucks and transported off the construction site until it reached the excavated bottom. The drilling rig for the geothermal probes is now in operation there and has already drilled more than half of the deep boreholes. At the same time, preparations for the laying of the collector pipes and the first foundation sections have started. The objective is to complete the drilling and the crane foundation work before Christmas.

 