Saltenstrasse 1, Vienna – Construction progress

The work is in full swing and shows great progress. All sheet piling walls were installed at a depth of 12 metres, which closed the pit support all round. Depth drilling was also finalized, with a total of 25 wells drilled to a depth of 150 meters throughout the property. All preparations have therefore undergone so that the excavation can begin and the previous achievements are no longer hidden only in the soils.

 