In all areas of the building, the construction work is lively. While the underfloor heating is already being installed in staircase 2, the dry walls are being set up in staircase 1 and closed in sequence. At the same time, the exterior waterproofing on the balconies will be completed, the sun protection units will be installed and the facade above them will be built. After connecting the sewer pipes, the last section of the external scaffolding has now been assembled so that the work can proceed on all fronts.