The insulation on the facade is already almost completely in place while waiting for suitable weather conditions for the following working stages. For the time being, the construction work inside the staircase 1 is continuing without interruption. The underfloor heating was installed on the first floors and the concrete screed has been laid. Meanwhile, the backfill was placed above it and the last drywall walls were set up on the top two floors. At the same time, the sanitary and electrical installations are running in the entire building.