Saltenstrasse 1, Vienna – Construction progress

For the outdoor area, the installation of the balcony railings and their panel lining was completed. The final landscaping of the garden is now starting in this area. At the same time, the floor panels on the balconies and roof terraces will be installed. The substrate for the large green areas on the roofs has already been placed. Inside the building, the flooring tiles will continue to be installed for the various apartments. Meanwhile, the flooring in the garage and the sealant for the remaining rooms in the basement were prepared. As the next step, the preparatory work for the parquet floors is now in progress.

 