Stadlauer Strasse 64, Vienna – Construction progress 

Thanks to the good summer conditions, the shell of the building has been able to grow quickly! The upper floors have been partially completed up to the 4th floor, the shell of Stair 3 has already been finished. By November, all work on the shell will have been completed and the roof waterproofing will have been completed. While the top of the building is being built, the extensive installation work will be carried out on the floors below. From the cellar to the 1st floor, work to install the pipes for the water supply and sewage has already taken place. As the next step, the the total of over 1,100 windows that are currently being manufactured will be delivered to the construction site and installed, whilst the dry construction work will start at the same time.