Construction progress Wagramer Strasse 23.10.2017
The interior construction (drywall, electrical and building services installations) in component 1 is in full swing. The first drywall walls already form the rooms in the individual dwellings and the units are slowly taking shape.
The door frames for the apartment entrance doors were installed and the substructures for the flat steel railing were installed on the roof terraces before the sealing can be made.
In the row houses, in component 2, the windows were completely installed and the facade was started to be insulated. The drying work is completed and the screed is laid.
The installations for the building systems were produced on the basement floor.