Construction progress Wagramer Strasse

Construction progress Wagramer Strasse 24.11.2017

In part 1, the windows were completely installed and the drywall work is progressing rapidly. In the lower floors, the underfloor heating has started to be installed; soon the screed can be made here as well.

In component 2, the screed was completely laid and the painting work has started. The fall protection on the terraces as well as the partition walls will be installed soon.

 

<<see project>>