Construction progress Weinzingergasse

Construction progress Weinzingergasse 19.12.2019

In front of the house, the asphalt work was finished and the construction site equipment was removed so that the pavement can now be freely used again. In the interior, the tiling work is finished and the parquet floors are laid. At the same time, all contractors are busy completing their work. Following the Christmas break, the last finishing and final cleaning of the building are scheduled before the building is handed over to its future tenants.